A complex Brickell redevelopment involving structural reconfiguration, selective floor removal, rooftop pool additions, slab extensions, and garage alignment within an existing high rise structure.

Client

Form Group

Location

Brickell, FL

Category

Structural Redevelopment

Scope

High Rise Renovation

Project Overview

Structural Transformation In The Heart Of Brickell

One Broadway Brickell involved a major structural redevelopment within an existing high rise property located in the center of Brickell.

The project focused on significant structural modifications including the removal of two floors from the building core, rooftop pool additions, extending existing slabs, and raising the garage structure to align with neighboring amenity decks and updated circulation requirements.

Careful coordination between engineering, planning, and construction teams was essential to support the transformation while maintaining structural integrity and project efficiency.

01

The Challenge

  • Removing two floors from the center of an existing high rise required extensive planning, structural analysis, and carefully sequenced demolition.
  • Adding rooftop pools introduced additional structural and coordination challenges within an existing building framework.
  • Extending existing slabs required integration between structural design, field conditions, and constructability planning.
  • Raising the garage to align with neighboring amenity decks demanded careful elevation coordination and circulation planning.
02

The Approach

  • Developed phased structural sequencing for selective demolition and reconstruction within the existing tower.
  • Coordinated with architectural, structural, MEP, and construction teams to address integration challenges and existing building conditions.
  • Supported field driven solutions for slab extensions, garage alignment, and rooftop structural modifications.
  • Maintained focus on constructability, efficiency, and practical execution within a dense urban Brickell environment.
03

The Outcome

  • Supported the successful redevelopment and repositioning of an existing Brickell high rise through strategic structural planning and coordination.
  • Helped facilitate rooftop pool additions, expanded structural capacity, improved garage connectivity, and updated building functionality.
  • Contributed to a modernized property designed to support future residential and mixed use demands within Brickell.
One Broadway rooftop pool
Scope Highlights

Selective Floor Removal, Rooftop Pools, Structural Extensions, And Garage Reconfiguration

Strategic Group supported planning, coordination, constructability review, and field driven problem solving throughout a complex structural redevelopment within one of Brickell’s evolving high rise environments.